Work Weekend Reports

Report on April 24 & 25 Work Weekend

  • Work and repairs in Showerhouse

  • Work in Club House

  • Install vapor light on machine building

  • Clean and work around parking and Camping areas

  • Trail Work and Repair

 

 

Report on March 20, 21, 27and 28 Work Weekend

  • Thanks to all worker for the race prep work for "The Egyptian" Mid South Hare Scramble!

  • Trail prep and race setup made for a good event despite the wet weather.

 

Report on February 27 and 28 Work Weekend

  1. Move and Repair picnic tables

  2. Clean Pavilion

  3. Place trash cans and fire rings.

  4. Trail maintenance

  5. Race Preparations

 

REPORT ON OCTOBER 2009 Work Weekend

Thank you to all the members who worked hard this past work weekend. 11 workers.

PROJECTS WORKED ON OR COMPLETED THIS WORK WEEKEND (10/24-25) WERE:

  1. Manhole cover at Shower house installed and completed.

  2. Installed fencing behind shower house.

  3. Moved Fuel tank onto concrete pad.

  4. Clean and organize equipment barn.

  5. Remove debris, olive trees, and clean campings area behind machine building.

  6. Repairs and evaluate hydralics on skid steer.

  7. Trail Maintenance (ongoing)

  8. Bush hogging

  9. Gravel repair and blading to driveway, entrance road, and parking lot.

  10. Repairs to parking/pit area exit.

  11. Repairs to ditch crossing behind machine building.

 

REPORT ON SEPTEMBER 2009 Work Weekend 

PROJECTS WORKED ON OR COMPLETED THIS WORK WEEKEND (9/26-27) WERE:

  1. Wiring completed to pressure washer to complete the project.

  2. Machine building lean to addition completed.

  3. Kids MX Track Fence Completed.

  4. Bush Hogged field east of Parking Area. Some still left to finish.

  5. All equipment, four wheelers, and Rhino washed.

  6. Pressure washed front of Club House and Club House garage area.

  7. Trail Clearing work, which is still ongoing.

 

REPORT ON AUGUST 2009 Work Weekend

Thank you to all the members who worked hard this past work weekend. 

 It is always greatly appreciated. 

 We had 28 workers on Saturday (8-22), and 10 on Sunday(8-23).

 

PROJECTS WORKED ON OR COMPLETED THIS WORK WEEKEND (8/22-23) WERE:
 
1.  Motocross Track fence.  Completed.
 
2.  Cutting office doors in half.  Completed.
 
3.  Moved cooler back into the office.  Completed.
 
4.  Put key locker up in pole barn so qualified members can have access to equipment.  Completed.
 
5.  Mile markers taken down from last Mid-South race.  Completed.
 
6.  Water line & conduit were ran out to move pressure washer out of Motocross track driveway.  We still need to place 3"
      rock around it and have wire installed & hooked up.
 
7.  Lots of cleaning in club house and club house storage areas.
 
8.  Pressure washed picnic shelter.
 
9.  Trail clearing worked on, but this is on going.

10. Motocross track and Route 13 frontage mowed.